Steel drives Sky car park delivery

Posted on by in Weekly News

skypark160421Steel construction’s speed of delivery has come to the fore, as an 830-space multi-storey car park for media company Sky was built and operational in just 15 weeks.

Sky’s headquarters in Osterley, west London has undergone a major expansion with new offices and a new multi-storey car park both being constructed.

Bourne Parking was the main contractor and steelwork contractor for the car park.

“Normally the build programme would be much longer, but the client wanted the car park as quickly as possible so with four cranes working simultaneously for the steel erection we were able to achieve this fast programme,” explains Bourne Parking Senior Project Manager Greg Brown.

The car park measures 90m-long by 50m-wide and consists of seven levels, including ground floor and an open rooftop level.

The structure is a steel braced frame that supports precast flooring planks, with steelwork erected around a 7.5m by 16m grid pattern.

Prior to Bourne starting onsite, the plot for the car park had already been cleared with an old office block demolished under a separate contract.

Once the piling and the installation of ground beams had been completed, as well as the construction of two precast cores, the steel erection programme was able to begin.